Updated Tentative Schedule for the Front Street Paving Project

Image of recently paved street
Image of recently paved street

Tentative Schedule for the Front Street Paving Project

There will be things that force changes to the Schedule, UDIG locates, private work and other logistics.

  •      2   areas – Wiswall  done - open
  •      2   areas     -   Henrys , Sunset   done-open
  •      2   areas    - Post Office, db trends  done – open
  •      2   areas    - Medberry and Tea Kettle, Poured yesterday 4/19 covered and barricaded, to be Opened Mon 4/2 
  • Monday 4/24  DPW will dig out Northeast and Southwest Corners of Front at Bath Streets, same routine, dig/form/pour, cover and barricade.
  • Monday 4/24 ….Contractor for S. O’Brien will dig out and form, Tuesday pour sidewalk and curb in front of old Theater.
  • Following week DPW to continue to move West, with catch basin work continuing simultaneously as they go.
  • Other Storm catch basin work going on continually West of Bath Street to West High Street.