Updated Tentative Schedule for the Front Street Paving Project
Posted on: April 20, 2023 - 3:57pm
Tentative Schedule for the Front Street Paving Project
There will be things that force changes to the Schedule, UDIG locates, private work and other logistics.
- 2 areas – Wiswall done - open
- 2 areas - Henrys , Sunset done-open
- 2 areas - Post Office, db trends done – open
- 2 areas - Medberry and Tea Kettle, Poured yesterday 4/19 covered and barricaded, to be Opened Mon 4/2
- Monday 4/24 DPW will dig out Northeast and Southwest Corners of Front at Bath Streets, same routine, dig/form/pour, cover and barricade.
- Monday 4/24 ….Contractor for S. O’Brien will dig out and form, Tuesday pour sidewalk and curb in front of old Theater.
- Following week DPW to continue to move West, with catch basin work continuing simultaneously as they go.
- Other Storm catch basin work going on continually West of Bath Street to West High Street.