Updated Tentative Schedule for the Front Street Paving Project
Posted on: April 7, 2023 - 11:55am
Tentative Schedule for the Front Street Paving Project
There will be things that force changes to the Schedule, UDIG locates, private work and other logistics.
- 2 locations South side near Wiswall Complete and Open for Foot traffic
- 2 locations In front of Henry’s and Sunset Corner, poured, barricaded, to be opened Monday 4/10
- Next 2 locations crosswalk at db trends and Post Office Monday 4/10 dig/form/pour, barricaded until Mon 4/17
- Next 3 locations crosswalk at Whistling Kettle, Medberry Corner, Bath & Front northeast Corner Mon 4/17, dig/form/pour barricade until Mon 4/24
- +++ Note: There be a Water Service pipe replacement job also going on Monday 4/10 at the same time, (private) with DPW assistance, Front street will be Closed Only from Low St to Spring St …..hopefully only for the day.
- +++ The week of Monday 4/17 a property owner via Contractor will be replacing Sidewalk and Curb in front of the old Theater. (north side)
Other Storm catch basin work going on continually West of Bath Street to West High Street.