Tentative Schedule for the Front Street Paving Project
Posted on: April 3, 2023 - 11:46am
Tentative Schedule for the Front Street Paving Project
- 2 areas near Wiswall Park (South Side) complete, Barricades to be removed Tuesday 4/4
- Next 2 locations : in front of Henry’s and Post Office, Start Mon 4/3 dig/form/pour, barricaded until Mon 4/10
- Next 2 locations : Whistling Kettle and Sunset Café, Start Mon 4/10 dig/form/pour, barricaded until Mon 4/17
- Next locations : db Trends, Medberry Hotel, Parking Lot on the corner of Bath/Front , Start Mon 4/17 dig/form/pour, barricaded until Mon 4/24
- Storm Catch Basin work West of Bath Street and Manhole on Spring St happening simultaneously with the ADA sidewalk work mentioned above.