  • 2 areas near Wiswall Park (South Side) complete, Barricades to be removed Tuesday 4/4

 

  • Next 2 locations : in front of Henry’s and Post Office, Start Mon 4/3 dig/form/pour, barricaded until Mon 4/10

 

  • Next 2 locations : Whistling Kettle and Sunset Café, Start Mon 4/10 dig/form/pour, barricaded until  Mon 4/17

 

  • Next locations :   db Trends, Medberry Hotel, Parking Lot on the corner of  Bath/Front , Start Mon 4/17 dig/form/pour, barricaded until  Mon 4/24

 

  • Storm Catch Basin work West of Bath Street and Manhole on Spring St happening simultaneously with the ADA sidewalk work mentioned above.